Simple S-Curve
PROJECT TASK Thursday, 19 Jul 2018

List of Project Task

 
Project Title:Demo Plaza ProjectStart Date: 21 Sep 2016
Location:Street name - City nameFinish Date: 30 Nov 2016
Project Owner:My CompanyDuration: 70 days
Action StatusNo. # Task Name / Sub Task Name % Value Remark 28/0905/1012/1019/1026/1002/1109/1116/1123/1130/11
View  Edit  Del1 Clear the Site 2.46
Edit  Del  Del  1.1 - Clear the Site Area I 1.84
1.70
0.14
Edit  Del  Del  1.2 - Clear the Site Area II 0.62
0.62
View  Edit  Del  Del2 Form Foundations 2.57
1.60
0.97
View  Edit  Del  Del3 Foundation Utilities 11.75 Include Foundation Concrete
1.06
6.76
3.93
View  Edit  Del  Del4 Slab Casting 7.42
1.80
5.62
View  Edit  Del  Del5 Remove Forms 1.58
0.36
0.60
0.36
0.26
View  Edit  Del6 Frame Structure 30.26
Edit  Del  Del  6.1 - Frame Structure I 14.05 First Floor
10.25
3.80
Edit  Del  Del  6.2 - Frame Structure II 16.21 Second Floor
11.20
5.01
View  Edit  Del  Del7 Frame Roof 11.58
4.24
7.34
View  Edit  Del  Del8 Exterior Brick 10.25
7.05
3.20
View  Edit  Del  Del9 Internal Framing 3.55
1.18
1.18
1.19
View  Edit  Del  Del10 Install Doors and Windows 4.68 Include Frame & Panel
2.36
1.00
0.84
0.48
View  Edit  Del  Del11 Interior Finishes 6.56
0.94
0.82
2.82
1.98
View  Edit  Del  Del12 Painting Work 2.50
0.61
1.11
0.51
0.27
View  Edit  Del  Del13 Fixtures 1.86
0.31
0.31
0.31
0.31
0.31
0.31
View  Edit  Del  Del14 Equipment 1.70
0.40
0.20
0.14
0.14
0.14
0.14
0.14
0.14
0.14
0.12
View  Edit  Del  Del15 Clean Up 1.28
0.21
0.21
0.21
0.21
0.21
0.23
TOTAL (% Value Main Task) Excl. Status Freeze   100.00 Planning % Value  2.103.629.6720.6123.3117.9511.876.623.151.10
TOTAL (% Value Main Task) Incl. Status Freeze   100.00 Cumulative Planning % Value  2.105.7215.3936.0059.3177.2689.1395.7598.90100.00
Note : = Found remark dataActual % Value  3.20 3.52 4.50 20.35 18.87 13.58 18.47
Cumulative Actual % Value  3.206.7211.2231.5750.4464.0282.49