Simple S-Curve
S-CURVE Tuesday, 22 May 2018

View S-Curve

Project Title:Demo Plaza ProjectStart Date: 21 Sep 2016
Location:Street name - City nameFinish Date: 30 Nov 2016
Project Owner:My CompanyDuration: 70 days

Task Description S-Curve of Planning & Actual
No. # Task Name / Sub Task Name % Value
1 Clear the Site 2.46
  1.1 - Clear the Site Area I 1.84
  1.2 - Clear the Site Area II 0.62
2 Form Foundations 2.57
3 Foundation Utilities 11.75
4 Slab Casting 7.42
5 Remove Forms 1.58
6 Frame Structure 30.26
  6.1 - Frame Structure I 14.05
  6.2 - Frame Structure II 16.21
7 Frame Roof 11.58
8 Exterior Brick 10.25
9 Internal Framing 3.55
10 Install Doors and Windows 4.68
11 Interior Finishes 6.56
12 Painting Work 2.50
13 Fixtures 1.86
14 Equipment 1.70
15 Clean Up 1.28
TOTAL (% Value Main Task)   100.00